This is our 24 days progress report of Desai and Khidkali site.
As you all are aware about this blog so if our other members wants to know more about project, you can reffer our site to them.
As we had a very nice AGM on 14th aug 2010 so if u want to see that meeting u can take help of our video documentation. For this you have to collect DVD from our office, We can not upload it on the site cause the size of the video is too large.
Desai Site :
1. Windmill is placed on A1 building. We will use the power which produce by windmill for staircase
lighting, common light, stilt parking and street light.
2. Drainage (Safety tank of A1, A2 & A3 building) work will complete soon as brick work is done and now plaster is going on.
3. A1 Lift wiring is complete, till next few days lift will be place.
4. A1 chamber work is in the process.
5. A2 interior work will be start soon.
6. A3 brick work will be start soon.
7. A4 7th slab is complete.
8. A5 2nd floor brick work and plaster is in process & 6th slab in progress
9. A6 1st floor workin progress & 6th slab in progress
10. A7 6th slab in progress & 2nd floor work is in progress.
KHIDKALI
28th no. Row house is in progress.
नमस्कार
ये हमारे पिछले २४ दिन का खिद्काली और देसाई साईट का अपडेट हैं
जैसा की आप सभी जानते हैं की अब हम इस ब्लॉग के जरिये हर १५ से २० दिन में जो भी कुछ काम साईट पे हो रहा हैं उसकी जानकारी सभी हमारे मेम्बेर्स को पहुंचाते हैं
१४ ऑगस्ट को हमारी वार्षिक सर्वसाधारण सभा हुई
अगर उसका विडियो आप को देखना हो तो आप जिद्न्यासा के ऑफिस में संपर्क करे
निचे दिए गए विडियो को ध्यान से देखे
No comments:
Post a Comment