Hello Members,
This is our 24 days progress report of Desai and Khidkali site.
As you all are aware about this blog so if our other members wants to know more about project, you can reffer our site to them.
As we had a very nice AGM on 14th aug 2010 so if u want to see that meeting u can take help of our video documentation. For this you have to collect DVD from our office, We can not upload it on the site cause the size of the video is too large.
Desai Site :
1. Windmill is placed on A1 building. We will use the power which produce by windmill for staircase
lighting, common light, stilt parking and street light.
2. Drainage (Safety tank of A1, A2 & A3 building) work will complete soon as brick work is done and now plaster is going on.
3. A1 Lift wiring is complete, till next few days lift will be place.
4. A1 chamber work is in the process.
5. A2 interior work will be start soon.
6. A3 brick work will be start soon.
7. A4 7th slab is complete.
8. A5 2nd floor brick work and plaster is in process & 6th slab in progress
9. A6 1st floor workin progress & 6th slab in progress
10. A7 6th slab in progress & 2nd floor work is in progress.
KHIDKALI
28th no. Row house is in progress.
नमस्कार
ये हमारे पिछले २४ दिन का खिद्काली और देसाई साईट का अपडेट हैं
जैसा की आप सभी जानते हैं की अब हम इस ब्लॉग के जरिये हर १५ से २० दिन में जो भी कुछ काम साईट पे हो रहा हैं उसकी जानकारी सभी हमारे मेम्बेर्स को पहुंचाते हैं
१४ ऑगस्ट को हमारी वार्षिक सर्वसाधारण सभा हुई
अगर उसका विडियो आप को देखना हो तो आप जिद्न्यासा के ऑफिस में संपर्क करे
निचे दिए गए विडियो को ध्यान से देखे
JIDNYASA CO-OP HSG SOCIETY
Friday, August 20, 2010
Monday, July 19, 2010
Report 26th June to 19th July
Hello Members,
This is our 20 days progress report of Desai and khidkali site.
Now we will all connect through this blog and you can see the updates of work of JIDNYASA Society.
Please tell others to see this blog, here you will find the details in English and Hindi language as well as you can watch the video where you find the detail work of Desai and Khidkali Site.
Following are some updates in these 15 days work:-
Desai - site
1. Drainage tank is almost complete.
2. Securities have been recruited on both site.
3. Staircase lighting of A1 is complete and soon we will install the windmill also.
4. A4 - 7th slab in process.
5. A5 & A6 - 5th slab in process.
6. A7 - 6th slab in process.
7. New Bldg A8 is going to construct soon.
Khidkali Site:-
1. B3 - 3rd slab is in process.
2. B4 - Plinth is completed.
3. Row houses are in progress.
नमस्कार
अब हम हर १५ से २० दिन में देसाई और खिद्काली साईट पे होने वाले काम की जानकारी इस ब्लॉग के जरिये ले सकते हैं नीचे दिए हुए विडियो को जरुर देखे.
This is our 20 days progress report of Desai and khidkali site.
Now we will all connect through this blog and you can see the updates of work of JIDNYASA Society.
Please tell others to see this blog, here you will find the details in English and Hindi language as well as you can watch the video where you find the detail work of Desai and Khidkali Site.
Following are some updates in these 15 days work:-
Desai - site
1. Drainage tank is almost complete.
2. Securities have been recruited on both site.
3. Staircase lighting of A1 is complete and soon we will install the windmill also.
4. A4 - 7th slab in process.
5. A5 & A6 - 5th slab in process.
6. A7 - 6th slab in process.
7. New Bldg A8 is going to construct soon.
Khidkali Site:-
1. B3 - 3rd slab is in process.
2. B4 - Plinth is completed.
3. Row houses are in progress.
नमस्कार
अब हम हर १५ से २० दिन में देसाई और खिद्काली साईट पे होने वाले काम की जानकारी इस ब्लॉग के जरिये ले सकते हैं नीचे दिए हुए विडियो को जरुर देखे.
Sunday, June 27, 2010
Report 19th June to 26th June
Hello All Members,
Now onwards we will connect through this Blogger Where you will get the weekly updates. you can also see the photos and current videos. So you can check this online and you will get our posting details through the SMS.
Please watch the video for current updates.
Thanks
Jidnyasa Co-op Hsg. Society.
नमस्कार
सभी सभासदोंका हार्दिक स्वागत,
अब आप सभी इस ब्लॉगर के हर हफ्ते काम की जानकारी ले सकते है यहाँ पे आप हर हफ्ते पुरे हुए काम के विडियो या फिर फोटो देख सकते हें और इस सभी काम की जानाकारी, मोबाइल के जरिये आपको समय समय पे दी जाएगी आप हमें यहाँ लिख भी सकते हें
फ़िलहाल आप नीचे दिए गए विडियो के जरिये जानकारी प्राप्त कर सकते हें
धन्यवाद्