Monday, July 19, 2010

Report 26th June to 19th July

Hello Members,

This is our 20 days progress report of Desai and khidkali site.
Now we will all connect through this blog and you can see the updates of work of JIDNYASA Society.
Please tell others to see this blog, here you will find the details in English and Hindi language as well as you can watch the video where you find the detail work of Desai and Khidkali Site.
Following are some updates in these 15 days work:-

Desai - site
1. Drainage tank is almost complete.
2. Securities have been recruited on both site.
3. Staircase lighting of A1 is complete and soon we will install the windmill also.
4. A4 - 7th slab in process.
5. A5 & A6 - 5th slab in process.
6. A7 - 6th slab in process.
7. New Bldg A8 is going to construct soon.

Khidkali Site:-

1. B3 - 3rd slab is in process.
2. B4 - Plinth is completed.
3. Row houses are in progress.

नमस्कार
अब हम हर १५ से २० दिन में देसाई और खिद्काली साईट पे होने वाले काम की जानकारी इस ब्लॉग के जरिये ले सकते हैं नीचे दिए हुए विडियो को जरुर देखे.